Portland Harbor CAD Cell and Dredge project moves forward

Aug 13, 2024

The Portland Harbor CAD Cell and Dredge project is set to proceed following the finalization of funding. Secured funding totals $25 million, including $10 million from the State of Maine, $1.45 million from the U.S. EPA, $6 million from the Maine Department of Transportation, $4 million from the City of Portland, $1 million from the City of South Portland, and $2.64 million in private fees.

This essential project will address sediment buildup around 47 waterfront properties, including piers, marinas, and public boat facilities. The dredging, estimated at 244,678 cubic yards, will take place over three years, with the contaminated material being disposed of in a confined aquatic disposal (CAD) cell. Portland City Manager Danielle West emphasized the project’s importance for the future of the working waterfronts in both Portland and South Portland.